07/01/2022
It’s been a long time since any updates have been posted about the new mill building but wanted to share some exciting photos and give a little rundown of the progress! All of the siding, shingles and insulation installed. The electrical wiring, plumbing, and the HVAC system are in place. All of the drywall is done and the next steps are for plastering to begin, interior doors, and some interior finish work. Hoping the mill equipment will be here by the end of January. It’s been very exciting to watch the new building go up and the prospect of getting our customers’ fiber back in the mill is thrilling. The crew from Hadden Fine Carpentry LLC has been amazing and we are lucky to have them. It’s awesome to see the weekly progress. We will continue to post more updates as we get closer to finishing the new mill! Thank you all for the love and support you’ve shown throughout this process. -SFF