17/07/2026
Hi everyone,
As promised, we want to make sure everyone on the street is kept in the loop. We’ve received an update regarding the ongoing works, scaffolding, and lighting from MCC and the Town Council.
Here is exactly where things stand right now:
Building Works & Scaffolding -
2 Church Street: The scaffolding license actually lapsed on June 30. The owner has requested an extension until July 31. The council is apparently trying to get a clear, full timeline of the works from the owner to make sure it matches that extension. If the owner doesn't provide clarity, the council is looking into their legal options to escalate the situation. ( owner the same as the Barton alley that was closed for 3 years )
4 Church Street - Nationwide: Works are ongoing here. The scaffolding license is currently valid until September 6.
10 Church Street: Works are also ongoing, with the scaffolding license valid until August 8 - an extremely long process.
Lighting & Street Clean
Street Lamps: MCC officers inspected the street and confirmed that all standard street lamps are fully working.
Overhead Feature Lighting: As you know, these are currently dead. This happened because the power supply was removed by the owner of 1 Church Street, and parts were disconnected due to the works at number 4. Council are apparently working on a new power supply and have suggested a temporary fix to get the overhead lights back on while the work at number 4 continues.
Weeding & Cleaning:
The next scheduled MCC street cleaning and weeding is set for today (July 17)? 🤔
Business Promotion & Signage -
Nationwide Signage Offer: Nationwide has offered to fund and provide extra signage in Church Street (and potentially around the wider town centre) to help direct foot traffic and visitors down our way.
Meeting on July 20: There is a meeting coming up this Monday, for church street residents and traders, where this additional signage will be discussed... along with our other concerns.
Just to clarify a point from the council's notes : They mentioned businesses couldn't make the previous council meeting, but we want to emphasise that it was a general council meeting, not a dedicated signage meeting. Most of us simply couldn't attend due to prior, unavoidable business commitments—especially since so many of us are working extra hours and taking on second jobs to compensate for the massive hit to our trade.
We will keep pushing for answers, especially regarding the timelines for numbers 2 and 4, and 10. We will share more info as soon as we get it but again...